Site A Erection
my Mass Timber Site A · on-site erection · WP-L01-ZA then WP-L02-ZA

Site A erection, scan, pick, set, in install sequence

The pre-assembled pieces from your STEP model are staged beside the slab, MEGANT plates already on, and the L01 CLT panel arrives with its four L02 floor-to-column connectors factory-fitted. For every piece, the rigger scans the QR that was burned into it back at the staging yard, the phone checks it against the install sequence, and only then does it go on the hook. The crane sets it, and the erectors guide it home and fix it. Columns, beams and CLT come from the model's own geometry, and the QRs decode to your 3DEXPERIENCE objects.

Site A · WP-L00 completeReady to erectSlab poured, anchors cast in
07:425G ▮▮▮
Site A · Erect
Loading site model…
00:00 / 00:00
Rigger, scans Erectors Crane operator

What the phone checks

Each glulam and CLT product carries a 109 × 109 QR, laser-hatched into one face. Read back from the STEP hatch, every one decodes to a 3DEXPERIENCE link: TimberDevSpace, the product's AecColumn, AecBeam or AecSlab object id.

The code is burned in the staging yard, on the gross blank, before any machining: a worker keys the element code into a handheld fibre marker and it hatches the QR into the face. So the same mark the rigger reads here is the one the CNC scanned to load that piece's program.

The QR identifies the product, not the instance. All eight beams are BEM‑022, and both A-line columns on a level share one product. So the app assigns the scanned piece to the next open slot of that product in the sequence, and it refuses a piece that belongs later. Click any staged piece to try it.

The steel kits have no QR in the model. They carry a printed kit tag made from their own install attributes, and the page labels them that way.

The crew

Rigger (orange hat). Scans every piece before rigging, then attaches the shackle, chokers or four-leg chain and signals the lift from a safe spot.

Two erectors (yellow). Set the base kits and L01 columns from the slab. They hang beams and land CLT from two scissor lifts, and work the L02 columns from the L01 deck once edge protection is up.

Crane operator (white). A mobile crane off the west edge of the slab, 19 m boom, luffing between 25 and 75°.

From the model, and assumed

From the STEP: every piece's geometry and final position, the MEGANT plates, clamping jaws, knife plates, pins and floor shoes, piece marks, grids and InstallSequence 1–13 per level, and the QR content. The QR's placement comes from the model too; when it gets burned is a process choice, and it now happens at staging rather than on the CNC.

Assumed for the scene: the crane, staging layout, rigging, lifts, stair tower and all timings. Columns and CLT are released with remote-release shackles. The MEGANT plates are shown factory-fitted (the model marks them InstallType=Factory); the clamping jaws go on after each beam is hung.

Corrected from the model: floor connectors go on in the factory. The model lists the four CON 400mmX400mm Floor to Column Connection assemblies as on-site units, L02 sequence 1–4, InstallType=InSitu. Each one clamps the CLT between a top plate and a bottom plate under the panel with four vertical M16 rods, so it can't be set from above once the panel is down. Here they are fitted to S-L01-A01B02-01 in the factory and ride in with it. Only the three horizontal M16 rods per column stay on site, as the L02 column fixings.